EXHIBITION SPACE [part_4]

The first thing I did as soon as I arrived school since no one arrives at 8, was to disassemble the Imac shelves so when the iMacs arrives we just need to place and re assemble. I also found dwardu the handyman and made sure the lock is fixed. So those were two lists of…

EXHIBITION SPACE [PART_3]

My job for today was to finish off two of the most important things in our exhibition space. The first thing I did was to buy clear varnish and finish the iMac shelves. They need another layer for sure, but they look totally different now and more appealing. After finishing the iMac shelves I gave…

EXHIBITION SPACE [PART_2]

My job for today was to have the table top finishes, the light installation fitted, and preparing the shades. The first thing I did in the morning was to go to Gozo to get the installation. I was very looking forward to finally see it hanging and prove that hard work pays off. Nicholas Farrugia…

EXHIBITION SPACE [PART_1}

Today the most important tasks were to fit all the iMac shelves and the book shelves. The day before some students tried to install some shelves but the had to be redone. After fitting¬†some of the shelves Marco and Joseph had argument about how secure they were. I took the responsibility to fit the iMac…

LIGHT FIXTURE

On Friday I could not attend to school. The reason was that we were very tight with time and I still had to finish the light installation. Since my workshop is based in Gozo I decided to leave Malta for the day and work on the light fixture. The fixture is made of two materials,…

MORE STUFF (Welding, Cleaning..etc)

While the others were retouching the rooms, the first thing I did in the morning was to measure the template. I needed ASAP to create a template for the table and calculate the amount of wood needed. I also finished the way finding stand by welding and extra 2 pieces of metal for stability. I…

DRILLING

While the other members were painting the rooms, my job for today was to finish the iMacs brackets so tomorrow they could be fitted. The only thing left for today was to drill all the holes in the brackets for the best secure and safest brackets to hold the iMacs

SHELVES BRACKETS

Today me and Marco met in Qormi to buy the holo sections, so that we can start working on the brackets. ¬†We bought 2 20*20*2 and cut them according to the needed size. As soon as we got to school we started welding the brackets and finished them. The remaining task is to drill the…

ASSEMBLING THE IMAC SHELVES

Today was one of the busiest day, but one of the most satisfactory one as well. Me and Marco managed to start and finish the iMac shelves. I am very proud that we managed to do the iMac shelves from start to finish ourselves. This was a challenge work with some equipment was something new….